Thursday, September 28, 2017

September 28th

Siding and Drywall!


Within the past couple of weeks the house has really taken shape. The drywall started going up a couple of weeks ago and siding as well as the slab in the garage was completed this week.  We were told by our project manager today that the house is scheduled for completion and walk through on October 25th and instructions regarding closing will be emailed out shortly, while closing should take place shortly after.  We were also told that beginning next week trim will be installed, painting will be completed, and tile/vinyl will be put down later in the week.



That's going to be quite the drop off. Now we need to find someone to put in steps after closing.




We Love the Garage! Don't really plan on parking cars in here, probably just more of an extension of the living space and work out space

Morning Room that we will convert into our Dining Room

Kitchen/Pantry with external exhaust

This bozo keeps getting in all the pictures

Master Bedroom

Thursday, September 14, 2017

September 9th

Finishing Framing

We were contacted by our project manager today who has done a great job of staying in contact with us and he told us we would have our Pre Drywall meeting on Wednesday.  We have noticed that you need to stay on top of the work that has been performed. Initially when framing our house, a window was not framed in until we brought it to our project managers attention but we do understand that there are a large number of houses being built at once. I believe 6 houses have already completed and approximately 12 more are under construction.






Master Closet


Master Bedroom

Master Bedroom



2nd Bedroom

Dining Room



3rd Bedroom



August 31st- September 7th

House Framing







































August 11th

Foundation





 





August 4th

Homesite Cleared


July 31st

Pre Construction Meeting


Sorry for the delay in posting, work has been extremely busy to start the year. Anyway, we had our pre construction meeting on July 31st. I don't think that this meeting is usually all that time consuming but we had a large number of questions and since this is our first home we had our project manager go over a number of things in full detail. We have so many questions about the process, I kind of feel sorry for our project manager, we are just a bunch of newbies.

Pre Construction Questions

1.     Will we be able to see inspection reports? These are available online through the county permit office.

2.     Where are the outside spigots (house bibs) going to be located? On the left and right sides of the house roughly in the middle.

3.     Will a termite treatment be done during construction? Yes

4.      Will the windows have screens? Yes

5.     Where will the attic access be located? In the third bedroom with a stair pull down. 

6.     Will there be a sump pump in the crawlspace? While some lots in our neighborhood will have them ours will almost certainly not need it. There will however be a French drain installed around the perimeter of the crawl space to drain away any moisture that gets in there.

7.     Where is the inside air handler located? In the attic, it will have an overflow pan and an overflow shut off valve.

8.     Do we need to buy a mailbox? The standard neighborhood model will be provided.

9.  How much flooring in the attic? Eight feet wide the length of the house

10.  Will there be smoke detectors or carbon monoxide detectors in every room? (Noticed on the other Sienna we walked through) Per code smoke detectors will be in every room and one carbon monoxide detector for the house on each floor.

11.  Will there be dimmer switches installed?No.

12.  What are the standard outside lights? Front porch light, back door light, and a front pole light with a photo cell to turn on automatically at sunset are standard. 

13.  Will there be a deadbolt on the door from the garage into the mudroom? No.

14.  How does the large garage door lock? Metal slider latch.

15.  Will the landscaping and sod be completed prior to closing? What sort of plants come with it? Will the backyard be seeded?  Weather permitting it will be done otherwise as soon as possible after closing. There will be a maple tree in the front yard along with basic box shrubs around the front.

16.  How is the subfloor attached? Is it just nails or glue/adhesive as well? Adhesive will be used along with nails and screws. 

18.  What companies are providing cable/phone/internet to the neighborhood? Cox Communications and Verizon FiOS have run lines. 

19.  Where will the main water shut off be located? In the garage.

20.  Best way to reach project manager with questions? Cell number was provided; M-F typically 8-5 each day.

21.  Will there be gutters? Yes, there will be gutters.

22.  Will we be able to keep a copy of blueprints? No, but we can get a copy from the county office

23.  How far back into the tree line does our property extend? Approximately 35-40 feet from the farthest point of our house; We decided to pay extra to have a larger portion of our lot cleared

24.  Can we place instead of double sink a single sink in the kitchen? No.

25.  Will there be any electrical boxes on our lot? Will they be covered at all? Yes, there will be one box but he wasn't sure if there would be any coverage around the utility box. From looking around the rest of the neighborhood it does appear to have some mini trees surrounding the box

30.  Will there be a plumbing line run to the refrigerator spot? Yes

October 25th

New Home Orientation Today was the new home orientation in which we reviewed everything from lawn care, warranties, operation of housin...

Followers